Digging the Pit Continues

For the last couple of weeks the community volunteers have been working on a water project for the village. But now they are back on the toilet block project. We really need to congratulate the workers who are still digging out the pit. When finished it will be 40′ by 10′ by 8′ deep (12m x 3m x 2.5m). That is about 100 tonnes of soil that needs digging out and as you can see it needs pickaxes to soften the laterite (the reddish iron and aluminium rich soil) .

Pickaxes hard at work
Only about 5′ (1.5m) to go!

Loading